 Re: Field 51 Construction Days
 
 8/24/2008 8:33:57 AM
51
67 posts


Re: Field 51 Construction Days

We're still behind on getting the apron in. Hoped to have it poured already, but only the ground work is done.

The forms are being made today (Sunday) and put up to day. Then sometime next week (if I can get enough hands) reschedule the cement delivery.

 

HELP NEEDED!!

 

Thanks - Norm

 8/25/2008 10:51:20 AM
51
67 posts


Re: Field 51 Construction Days

Looks like we'll be pushing our first

play day out to September 6th?

The only thing I need to wrap up is the paved apron.

If this doesn't get done soon I'll have to push the Sept 6th game back yet again.

The only thing left is to spread the cement into the forms.

Want to help with the prep work?

I need 2-3 people for 1/2 a day this week.

Shoot me an e-mail

mailto:ref@field51.com

 8/26/2008 1:11:03 PM
51
67 posts


Re: Field 51 Construction Days

Thursday 8/28/08

 

We'll be pouring the cement for the paved apron.

From 9:00am to 1:00pm

If you have time, stop by - do a little work - and sign your name.

It'll be a moment in time..... When we finally get over this last hurtle.

 

Thanks to everone that has help out to this point!

As you all know it's been a long road to here.

 

 